Main items of Cua Luc No.3 Bridge project to be accomplished by the end of 2021

Having been launched since late 2020, Cua Luc No.3 Bridge project has been delayed due to some changes in design for better landscape. All of the constructors have been speeding up the progress to finish main items of this project by the end of this year.

Cua Luc Bridge 3 crossing Dien Vong River (Cua Luc Bay) has a total length of 2.6km and 6 lanes. The first point connects the main road of FLC Urban Area at Ha Khanh ward and the ending point intersects the national highway No. 279 in Ha Long city.
Cua Luc Bridge 3 crossing Dien Vong River (Cua Luc Bay) has a total length of 2.6km and 6 lanes. The first point connects the main road of FLC Urban Area at Ha Khanh ward and the ending point intersects the national highway No. 279 in Ha Long city.
The main bridge is 170m long, the contractors have completed the construction of the lower part and the main pillar in the middle of the river.
The main bridge is 170m long, the contractors have completed the construction of the lower part and the main pillar in the middle of the river.
Works started on the pouring of concrete to burn beams at the position of 2 pillars in the middle of the river on November 13.
Works started on the pouring of concrete to burn beams at the position of 2 pillars in the middle of the river on November 13.
Workers are fabricating the steel arch system in the middle of the river with a height of 40m and a width of 90m.
Workers are fabricating the steel arch system in the middle of the river with a height of 40m and a width of 90m.
At the section leading to the main bridge, 100 out of 758 bored piles have been completed, 9 out of 119 pedestals, 5 out of 119 girder beams of the lower structure have been completed.
At the section leading to the main bridge, 100 out of 758 bored piles have been completed, 9 out of 119 pedestals, 5 out of 119 girder beams of the lower structure have been completed.
82 out of 182 Super T beams have been installed at the section leading to the main bridge
82 out of 182 Super T beams have been installed at the section leading to the main bridge
The contractor is carrying out load testing for the 2nd phase of T6 and T7composite blocks. It is expected that the main bridge deck will be covered with concrete in December 2021, meaning that the main bridge's items will be basically completed and the construction of steel arch items will start then.
The contractor is carrying out load testing for the 2nd phase of T6 and T7composite blocks. It is expected that the main bridge deck will be covered with concrete in December 2021, meaning that the main bridge's items will be basically completed and the construction of steel arch items will start then.