The 1st phase of the riverside road project to be completed in 2025

Wednesday, 12/03/2025 | 11:34:41 [GMT +7] A  A

The project of constructing the riverside road connecting Quang Yen town's Dam Nha Mac intersection to the Provincial Road 338 has currently been resumed after a suspension. It is expected that the project will have been accomplished by the end of 2025.

Nearly 50% of the total work volume for the Riverside Road (Phase 1), connecting Dam Nha Mac to Provincial Road 338, has been completed.
Work has been done at the bridge approaches
Contractors have currently carried out excavation of soft soil, backfilling with fine sand, medium sand, installing drainage wick, and have completed nearly 3 km of K95 subgrade construction at the beginning of the route.
Soft soil treatment work
Nearly 2 kilometers of the route have been embanked with preload soil, awaiting settlement for an estimated period of 6-8 months.
The section at the Dam Nha Mac intersection, connecting Riverside Road Phase 1 with the Ha Long - Hai Phong Expressway, has been completed.

By Do Phuong