Sat, 23rd Nov 2024 23:49 (GMT +7)

Speeding up the construction progress of Quang Ninh’s two largest intersections

Friday, 18/03/2022 | 14:57:45 [GMT +7] A  A

With a total area of ​​more than 160 hectares, Dam Nha Mac and Green Ha Long intersections are the two largest intersections in Quang Ninh province. Once completed, these two projects are expected to effectively connect the province’s western region with the highway of Ha Long - Hai Phong - Hanoi as well as boost the development of Quang Yen coastal economic zone.

Dam Nha Mac intersection is a branch of the route connecting the riverside road with Ha Long - Hai Phong highway at Km20+050. Located on an area of 83.4 hectares, the intersection is designed with a complete asterisk-type interchange including 8 branches with a total length of 8,095 kilometers.
Dam Nha Mac intersection is a branch of the route connecting the riverside road with Ha Long - Hai Phong highway at Km20+050. Located on an area of 83.4 hectares, the intersection is designed with a complete asterisk-type interchange including 8 branches with a total length of 8,095 kilometers.
Up to now, the expansion of the tunnel on this expressway has been completed.
Up to now, the expansion of the tunnel on this expressway has been completed.
The construction site includes many ponds, lagoons and soft ground, thus, it has taken constructors lots of efforts to carry out the project.
The construction site includes many ponds, lagoons and soft ground, thus, it has taken constructors lots of efforts to carry out the project.
The Green Ha Long intersection is another branch connecting the riverside road with the Ha Long - Hai Phong highway and the second largest intersection in Quang Ninh. This intersection is also designed with 8 branches covering an area of 77.6ha.
The Green Ha Long intersection is another branch connecting the riverside road with the Ha Long - Hai Phong highway and the second largest intersection in Quang Ninh. This intersection is also designed with 8 branches covering an area of 77.6ha.
At the construction site of the overpass on the Ha Long - Hai Phong highway with a length of 1.5 km, constructors are constructing pillars, abutments and casting the beam.
At the construction site of the overpass on the Ha Long - Hai Phong highway with a length of 1.5 km, constructors are constructing pillars, abutments and casting the beam.
Other works such as sand embankment and soft ground treatment are also carried out at the branches.
Other works such as sand embankment and soft ground treatment are also carried out at the branches.
The asterisk-shaped branch connecting to the central road of the Green Ha Long Complex Urban Area Project invested by Vingroup is still on the adjustment stage.
The asterisk-shaped branch connecting to the central road of the Green Ha Long Complex Urban Area Project invested by Vingroup is still on the adjustment stage.

By Do Phuong