Fri, 22nd Nov 2024 16:50 (GMT +7)

Speeding up the construction of Ben Rung Bridge connecting Hai Phong with Quang Ninh

Wednesday, 15/02/2023 | 11:28:26 [GMT +7] A  A

Having been launched since May 13, 2022, the project of Ben Rung bridge is expected to become a driving force for regional development and creating jobs for many people when it is put into operation.

The bridge, spanning the Da Bach River, has a total investment of nearly 2 trillion VND (86.6 million USD). The bridge measures over 1.87km in length and 21.5m in width with six lanes.

It is expected that the bridge will have been put into operation by the end of 2023 and it will become a driving force for regional development and creating jobs for many people.

The bridge, spanning the Da Bach River, has a total investment of nearly 2 trillion VND (86.6 million USD). The bridge measures over 1.87km in length and 21.5m in width with six lanes.
The project has currently accomplished about 30% of its total workload.
13 out 19 bridge poles have been constructed in the area of Quang Ninh province.
These beams are being casted on-site to save time and meet the project progress.
Three main poles in the heart of the river.
The project is scheduled to have been completed by the end of 2023.

By Do Phuong