Currently, the project progress of Provincial Road No 342 has been speeding up to ensure that the road can be open to traffic within 2023.
The project to renovate and upgrade Provincial Road No. 342 through Ba Che district has a total length of nearly 21km. The starting point links to Ha Long city’s Ky Thuong commune at Km37+50 and the ending point connects with Bac Lang commune, Dinh district Lap (Lang Son province) at Km58+405.Contractors have currently mobilized 45 excavators, 18 bulldozers, 25 rollers, 70 trucks, 9 sets of drilling rigs, 20 generators. 272 engineers and construction technicians have worked on the whole route.
Workers and technicians are preparing for the concrete pouring procedure of 17 piles at Khe Lu bridge.Building materials have already been transported to the construction site.
Constructing bridges and culvertsAfter more than 2 months, the construction project has so far reached over 20% of the workload, contractors are determined to complete the project in 2023.