Ha Long - Van Don expressway from height

Wednesday, 30/05/2018 | 09:16:33 [GMT +7] A  A

Ha Long - Van Don expressway, a key transport project of Quang Ninh province, connecting the Hanoi - Hai Phong - Quang Ninh economic triangle, boosting the development of Quang Ninh and the Northern Key Economic Region.

After over two years of construction, to date, more than 93 percent of the work has been fulfilled. The contractors have launched campaigns for each components of the project with the aim of speeding up the progress.

The first point of the Ha Long-Van Don Expressway connects Ha Long-Hai Phong expressway and the National Highway 18.
The first point of the Ha Long - Van Don Expressway connects Ha Long - Hai Phong expressway and the National Highway 18.
Some parts of the road have been basically completed and qualified to be in operation.
Some parts of the road have been basically completed and qualified to be in operation.
The package N0 6 by Licogi JSC was asphalted in February. Curently, the contractor is enhancing machines and man power in order to support other packages so that they could be fulfiled as planned.
The package N0 6 by Licogi JSC was asphalted in February. Curently, the contractor is enhancing machines and man power in order to support other packages so that they could be fulfiled as planned.
The Cam Y 380-meter flyover through the Highway 18 has been completed.
The Cam Y 380 - meter flyover through the Highway 18 has been completed.
Dong La intersection connects Ha Long-Van Don highway with National Road 279 and Ha Long city.
Dong La intersection connects Ha Long - Van Don highway with National Road 279 and Ha Long city.
Cam Hai bridge, the major component of the Ha Long-Van Don highway project was fulfiled in March, 2018.
Cam Hai bridge, the major component of the Ha Long - Van Don highway project was fulfiled in March, 2018.
The contractors are concentrating on consolidating, ensuring the technical safety of the wholy project so that it could be fully completed by June.
The contractors are concentrating on consolidating, ensuring the technical safety of the wholy project so that it could be fully completed by June.

 Article by Do Phuong